The Square D QO Value Pack 200 Amp Main Breaker 42-Space 42-Circuit Convertible Indoor Plug-on Neutral Load Center for Plug-on Neutral breakers is UL listed for residential, commercial and industrial power distribution Engineered for a quick Plug-on Neutral breaker connection on every circuit, fewer. Apr 29, 2010 Electrical Panels: New Installation of a 200 Amp Square D Electrical Panel. How to Wire an Electrical Panel - Square D. Square D QO Plug-On Neutral 200 Amp Main Breaker 30-Space 30-Circuit. Dec 11, 2010 Only Square D style circuit breakers fit in a Square D style panel box. Square D circuit breakers and panels use a square with a capitol D inside as an identification marker. Three wires enter a residential Square D service panel from the electric meter; two 120-volt hot wires and a neutral. These wires connect to bus bars. Square D Circuit Breakers Categories. Southland carries one the largest selections of Square Molded Case Circuit Breakers in the US.Southland Electrical Supply supplies new surplus and professionally reconditioned Molded Case Circuit Breakers but is not an authorized distributor for Square D. Square D 200 Amp, 60 Spaces 80 Circuits Maximum Square D QwikPak Panel Package with Breakers.
Sep 18, 2013 How to Wire an Electrical Panel - Square D Battle of the Tools. Unsubscribe from Battle of the Tools? Cancel Unsubscribe. Subscribe Subscribed Unsubscribe 12K. I have an old 200 amp breaker box in my house that I am remodeling and I need to install a new square d breaker box. Is there a way to do it without loosing power to the house while it is completely r.
Square D 200 Amp Meter Main Combo
Square D 200 Amp Service Panel
FACTS:
I need the additional capacity to finish a basement, and for other projects later like hot-tub and outdoor lighting. I have not had any problems with the existing panel. I simply want more capacity, and a higher quality panel. I also want to add a generator transfer switch, and whole house surge protection.
I have limited electrical experience, I have installed and replaced outlets. I have wired up small electronics, built PC's etc. I have no formal training as an electrician, but I can follow instructions, and plan to research the process thoroughly. The job will need to be inspected and I plan to adhere to NEC 2011, as specified in my city code. I want to use this book as a guide and reference.
The service is underground.
I want to replace the panel with a Square D QO OR Homeline 200 amp combination service entry and load center and associated breakers.
I want to replace the combo panel with a Millbank Heavy duty 320 amp meter base (standalone) and add two 200 amp Cutler Hammer CH load centers.
I have received quotes in the range of $4000 and up to do this (without transfer switch or surge protection,) which is why I am exploring the DIY option. I am however, unwilling to electrocute myself.
I can pull a permit from my municipality and do it as 'homeowner as contractor.' This work will not be done without a permit.
My local utility will work with me as long as I pull the 'homeowner as contractor' permit. I can get access and speak to my local utility engineer through my utility's builder line. The builder line agent I spoke with said what I want is a disconnect/reconnect. There is a fee associated with that, as I would expect.
THE BIGGEST PROBLEMS:
It appears that if the utility just pulls the meter, the line side will still be energized. I am uncomfortable having to move these to a new service entry. Do electricians move it over hot? Is there a way the utility can de-energioze the line for me to move it over? This is pretty much a deal killer for me unless there is a very safe technique I can find.
I do not understand grounding fully. It appears according to the NEC 2011 I will need to add two additional grounds (I have two in place.) I would appreciate any advice on this (if we decide it feasible for me to even do this project.)
THE BIG QUESTION:
Should I even attempt this? Is there a way to overcome the big safety issue of the line side being energized? Can they disconnect the line at the source? Will they do it if they can?
Another option is to replace the main breaker in the GE panel (currently 150 amps) with a 200 amp breaker. The enclosure will support a 200 amp breaker, and provides the part number. They are available for about $150.00. I could still upgrade service and be safe on the load side with the meter pulled by the utility.
What say the DIY hive? I can provide photos of the existing service if helpful.